|
|
 |
TR 1-99: DoD Acquisition Management Metrics |
 |  |
| |
Cost and Schedule Overruns
. Figure 2 is an updated version of the same figure that appeared in the
original research report. It shows cost and schedule overruns in the form of
the ratio of actual cost or schedule to planned cost or schedule. A program
that completed EMD essentially on cost and on schedule would have a ratio of
1:1 for both cost and schedule. Hence the smaller dotted line square in Figure
2 is the loci of all programs that came in on cost and on schedule. Data
points inside this square indicate programs that under ran cost and schedule.
The larger dotted line square is the loci of all programs with a ratio of 2:1;
that is, programs that completed EMD with exactly a 100 percent overrun in
cost and in schedule. To convert a ratio reading from Figure 2 into the
applicable overrun, subtract 1, and multiply by 100. For the 33 programs
contained in Figure 2 , the average cost overrun was 40 percent and the
average schedule overrun was 62 percent for the entire period from 1980 to
1996.

As indicated earlier, some valuable
insight into trends and the dynamics of the DoD acquisition system can be
obtained by recording this data in three separate-year groups, and to a lesser
degree, by individual Service. Figure 3 shows the cost and schedule overrun
averages for the three-year groups used in this report. An initial observation
is that cost overruns were the greatest, and schedule overruns the least
during the Cold War years ending in 1989. Since then, cost overruns have been
less than schedule overruns. This cost overrun trend agrees with Rich and
Dews' findings for programs in the 1960s, although our schedule overrun figure
is higher. Figure 4 shows that U. S. Army programs had less cost and schedule
overruns than the other Services. A superficial possible reason for this is
the general perception that Army equipment is less complex than the other
Services.


DoD average cost and schedule overruns
of 40 percent and 62 percent at first glance may not appear to be good.
However, when you factor in complexity of the development, and schedule
pressures this in fact may not be too bad. In fact, when compared to other
major projects, DoD acquisition cost management is among the best. Figure 5
shows DoD major weapon systems to have a cost overrun of approximately 38
percent, close to our 40 percent figure.
 (click image to enlarge)
Lastly, if cost and schedule overruns
are looked at in Total Quality Management (TQM) terms, and if 100 percent
overruns are considered the statistical process control acceptable limits of a
DoD acquisition system under control, the average cost overrun is halved to 19
percent and the average schedule overrun drops to 34 percent. That is, we
eliminate the nine programs that had cost or schedule overruns of over 100
percent. Programs over the acceptable process control limits could be handled
by some other extraordinary process. Our research methodology allows the
control limits to be set at any acceptable level and the resultant average
cost and schedule overruns can be obtained.
|
 |
|
|
| |
| |